Station |
Construction Started |
Construction Ended |
---|---|---|
Brentwood |
September 2020 |
Winter 2021 |
Victoria Park/Stampede | August 2021 | 2023 |
Anderson |
January 2018 |
June 26, 2019 |
University |
January 2018 |
April 8, 2019 |
SAIT /ACAD / Jubliee |
July 2017 |
February 19, 2019 |
Barlow / Max Bell |
September 2017 |
May 21, 2019 |
Zoo |
September 2017 |
Mar 8, 2019 |
39 Avenue |
April 2018 |
July 24, 2019 |
Rundle |
June 2016 |
December 2017 |
Marlborough |
June 6, 2016 |
December 2017 |
Renovations to the Brentwood station pedestrian bridges started in September 2020 with an anticipated completion date of winter 2021. During construction the station will remain open and CTrain service will not be impacted.
Renovations will include:
For the latest information on impacts to foot traffic or accessibility options, visit service updates or follow us on Twitter: @calgarytransit
Renovations to the interior and exterior of Anderson Station began in January 2018, and were completed in June 2019. CTrain service continued throughout construction, and the platform remained open with access from the north entrance (track crossing).
Upgrades to the station included:
Renovations to the interior of University Station began in January 2018 and were complete in April 2019. The station remained open during renovations with no disruption to CTrain service.
Upgrades to the station included:
Renovations to SAIT /ACAD / Jubilee Station began in July, 2017 and were complete in February 2019. The platform remained open during renovations with no disruption to CTrain service.
Upgrades to the station included:
Renovations to Barlow/Max Bell Station began in September 2017 and were complete in May 2019. The station remained open during renovations with no disruption to CTrain service.
Upgrades to the station included:
Renovations to Zoo Station began in September 2017 and were complete in March 2019. The station remained open during renovations with no disruption to CTrain service.
Upgrades to the station included:
Renovations to 39 Avenue Station began in April 2018 and were complete in July 2019. The station remained open during renovations with no disruption to CTrain service.
Upgrades to the station included:
Renovations to the interior of Rundle and Marlborough stations began in June 2016 and were completed in December 2017. Both stations remained open during construction and were renovated at the same time.
Upgrades to the stations included:
For more information, view Rundle & Marlborough Renovations - Frequently Asked Questions.
Why are these stations being renovated and how is it funded?
Rundle and Marlborough – These are two of the busiest and oldest stations on our system. They opened in 1985 and were due for life cycle upgrades. Funding for these renovations was primarily obtained through grants from the Provincial government and City funding.
Anderson, University, SAIT/ACAD/Jubilee, 39 Avenue, Zoo and Barlow/Max Bell – In 2016 we received funding from the Public Transit Infrastructure Fund to complete CTrain station upgrades. These six stations were chosen for renovations based on their need for lifecycle upgrades.